Network Rail has released a timelapse video to mark the one-year anniversary of the opening of Birmingham New Street station.

The video condenses five years of the station’s transformation into five minutes and highlights various construction milestones reached along the way.

The five-year £750M redevelopment project fully opened to the 170,000 daily passengers on 20 September 2015. Grand Central, the shopping and dining hub situated above the station, opened a few days later on 24 September.

The revamped station saw the creation of a huge passenger concourse, five times the size of London Euston’s, which is overlooked by the new atrium roof that floods the concourse with natural light.

The station’s platforms are now brighter and more minimalist, allowing for greater and easier passenger movement. Entrances to the city centre have also been improved.

New Street Station also features 40 shops at concourse level, with the Grand Central shopping and dining hub situated above it, which includes one of the largest John Lewis department stores in the country.

The original station was only designed to cope with 60,000 a day when it was last rebuilt in the 1960s. The redeveloped station can now cope with up to 300,000 visitors a day.

It is the busiest station outside the capital and is the busiest interchange station in the UK with a train leaving the station every 37 seconds.


The area surrounding the station is also being regenerated, with investment being made in new shops, bars and restaurants. Planning permission has also been granted for the creation of a 26-storey hotel near the station’s Southside entrance.

Work is still ongoing on the transformation, as work continues on the redevelopment of the station’s 12 platforms. Platform 11 will be the last to be completed and will reopen to passengers in mid-October.

Work on the southern hub that will provide an exit-only feature to the station giving direct access to Hill Street from the Navigation Street footbridge will also be finished by the end of October.

A year on and Network Rail research shows that New Street station currently enjoys an 88% passenger satisfaction rate – a record high for the station.